Asbestos Management Report |
|||
AHERA Record of possible exposure due to activity. Activities may include cleaning, fiber release, encapsulation, enclosure, repair, surveillance, inspection, renovation or maintenence. N/A: Not Applicable N/R: Not Required | |||
Date of Activity | Project Activity | Air Measurements | Respiratory Protection |
---|---|---|---|
Nov 18, 2015 | Demarais Environmental reinspection report completed and logged | N/A | N/R |
Nov 13, 2015 | Demarais Environmental completes reinspection | N/A | N/R |
Nov 5, 2015 | Joy Perkins does inspection | N/A | N/R |
Nov 5, 2015 | Demarais Environmental contracted to complete Reinspection report | N/A | N/R |
Nov 4, 2015 | Derrick completes Asbestos Awareness Training general and building under LEA 2hr | N/A | N/R |
Nov 4, 2015 | Surveillance walkthrough - Rondeau/Carter | N/A | N/R |
Nov 4, 2015 | Dan Rondeau completes Certified Asbestos Awareness Training 2 Hr. | N/A | N/R |
Oct 26, 2015 | Dan Rondeau becomes LEA | N/A | N/R |
Sep 8, 2015 | Community Awareness of AMP through portal | N/A | N/R |
June - July 2014 | Floors stripped and waxed - Rondeau | N/A | N/R |
Sep 2, 2014 | Community Awareness of AMP through portal | N/A | N/R |
August 2014 | Surveillance walkthrough - Carter | N/A | N/R |
July - August 2014 | Floors stripped and waxed - Fanjoy/Carter | N/A | N/R |
Sep 3, 2013 | Community Awareness of AMP through portal | N/A | N/R |
August 2013 | Surveillance walkthrough - Carter | N/A | N/R |
July - August 2013 | Floors stripped and waxed - Fanjoy/Carter | N/A | N/R |
July 2013 | Rooms 20 & 21 Tiled over with VCT, no disruption | N/A | N/R |
Jun 15, 2012 | Bob Jeffers retires as LEA, Bob Carter takes over | N/A | N/R |
Sep 4, 2012 | Community Awareness of AMP through portal | N/A | N/R |
August 2012 | Surveillance walkthrough - Jeffers/Carter | N/A | N/R |
July - August 2012 | Floors stripped and waxed - Carter | N/A | N/R |
Sep 6, 2011 | Community Awareness of AMP through portal | N/A | N/R |
August 2011 | Surveillance walkthrough - Jeffers/Carter | N/A | N/R |
July - August 2011 | Floors stripped and waxed - Carter | N/A | N/R |
Sep 7, 2010 | Community Awareness of AMP through portal | N/A | N/R |
August 2010 | Surveillance walkthrough - Jeffers/Carter | N/A | N/R |
July - August 2010 | Floors stripped and waxed - Carter | N/A | N/R |
Jan 14, 2010 | AHERA Inspection Report received | N/A | N/R |
Dec 14, 2009 | Asbestos Inspection by Tim Hunt, Desmarais Environ. | N/A | N/R |
Sep 30, 2009 | Community Awaerness of AMP | N/A | N/R |
Sep 15, 2009 | Asbestos Awareness Training (building) 1 hour Corey P. | N/A | N/R |
Sep 8, 2009 | Awareness Asbestos Training (general asbestos training)1 hour Corey P. | N/A | N/R |
Sep 5, 2009 | Bob Jeffers becomes LEA | N/A | N/R |
Sep 5, 2009 | Awareness Asbestos Training (general asbestos training and building)2 hour Jeffers | N/A | N/R |
Sep 5, 2009 | Awareness Asbestos Training (general asbestos training and building)2 hour Carter | N/A | N/R |
Sep 3, 2009 | Meeting and walk through with State Inspector (M Yin) | N/A | N/R |
July - August 2009 | Cores through floor to run gas line for science.
Coring completed with water fed coring drill. | N/A | N/R |
August - November 2007 | Renovation of building for use as a school. Involves removal of walls, removal of rugs. Covering of floors. | N/A | N/R |